IN THE HIGH COURT OF MALAWI
PRINCIPAL
REGISTRY
CIVIL
CAUSE NO. 3695 OF 2000
BETWEEN:
E J C KALESO
t/a RELIANCE
HOUSE HOLD PEST CONTROL………PLAINTIFF
AND
NAMING’OMBA TEA ESTATES LTD ……………………DEFENDANT
Msiska,
Counsel for the Plaintiff.
Msowoya,
Counsel for the Defendant
This is
this court’s order on the assessment of damages herein pursuant to a consent
judgment in the plaintiff’s fovour dated 27th November, 2001 for
damages for fumigation services rendered by the plaintiff the the defendant at
the defendant’s own request. The
plaintiff had been hired to fumigate the defendant’s cottage against
termites. The plaintiff did the termite
proofing. He initially charged the sum
of K258,067.50 for his services. But on
the defendant’s contending that the
charges were too high the plaintiff reduced them to K129,033.75. The plaintiff allegedly spent around
K56,000.00 on a material used in the fumigation although that was not substantiated
by any documentary evidence like cash sale for purchase of such materials.
The
plaintiff produced an invoice describing the work done of drilling holes,
injecting chemicals therein and sealing them and indicating the price. The plaintiff could not explain the proper
basis of his charges herein in terms that could be understood clearly. This was in contrast to the explanation
given on the charging system by an expert witness from the fumigation trade who
has requisite experience in the trade.
That witness explained the charging system as being per hole drilled on
the premises and injected with the required termite proofing chemical. When chemicals are properly injected into
the drilled holes on the intended premises it takes many years for termites to
resurface. Yet in the present case it
only took from November, when fumigation was done, to the following January
when termites were seen on the defendant’s premises again. Hence showing that the plaintiff did not
properly do his job.
Further,
after normal drilling of holes for termite proofing and after properly filling
them with the requisite properly diluted chemical, traces of the anti-termite
chemicals can be seen on the site of the holes but that was not the case herein
when the plaintiffs’ work was inspected by the expert witness 3 months after it
was done.
The
plaintiff could not specify the number of holes he had drilled.
This court
is of the view that the expert witnesses report herein ought to be attached a
lot of weight. It systematically
analyses the plaintiff’s work. The
plaintiff ought to have drilled 312 holes around the defendant’s old cottage
instead he drilled 69 holes only representing about 23% of the recommended
number of holes. The plaintiff also
completely ignored to do an ant-termite treatment to the defendants’ old
cottage known as trench treatment. And
with regard to the defendant chairman’s cottage the plaintiff drilled 71
instead of the recommended 397 holes representing around 18% of the recommended
treatment work required.
The expert
witness proposes that if he did the work it would cost as follows: defendant’s old cottage 312 holes at K50.00
per hole coming to K15,600.00, defendants’ chairman cottage 397 holes at K50.00
per hole coming to K19,850.00, transport 574 kms @ K13.20/km coming to
K7,576.80.
This
charge has been properly broken down and explained and is contrasted to the
plaintiffs’ charge which was not explained at all. The work of the plaintiff is clearly substandard as can be seen
from the explanation given by the expert witness herein. And it is clear that the termite proofing
was basically not done since within 3 months of the alleged termite proofing
termites appeared at the defendants premises.
What is the legal position in such cases on the plaintiffs’ recovery for
work done. In Nyadani
Buidling and Plumbing Contractors Company Limited v. Katri 9 MLR
154 the parties agreed that the appellant would fit window frames and panes at
a contract price of K210.00. The
appellant fitted the same save for 2 window frames and panes. The court ruled that the appellant was
entitled to recover for the rest of the work he had completed save for the 2
window frames not fitted. The court
overruled the Magistrate’s ruling that since the contract was for a lump sum
and the whole of the work have not been completed then the appellant was
entitled to nothing.
This court
has thought long and hard on the similarities of facts herein. And is of the view that the reasoning in the
above cited case can not apply in the present case. The present case involves the resolution particular problem of
termites. The result of the work sought
in the present case is different from that of simply fitting window frames and
panes.
This court
is of the view that the question that ought to be answered is whether the
plaintiff did substantially comply the contract herein warranting the payment
of the contract price or part thereof herein.
The reasoning in the English case of Bolton v Mahadeva [1972] 2 All ER 1322 seems more applicable in
the present case. The test of
compliance then becomes the nature of defects in the plaintiff’s work. In the present case the defects are so
glaring and of a substantial nature.
The plaintiff did not drill more than 30% of the holes necessary. The contract for work was not. Substantially compiled with to the extent
that within less than 3 months of termite proofing termites appeared on the
defendant’s premises. The defendant has
to engage somebody to redo the work herein.
And in the premises it appears that the correct decision is to award
nothing to the plaintiff as was the case in the case of Bolton v.
Mahadeva cited above.
This court
therefore declines to make any award to plaintiff.
Made in
Chambers at Blantyre this June, 2004
M A Tembo