IN THE HIGH COURT OF MALAWI
PRINCIPAL REGISTRY
CIVIL CAUSE NO. 2790 OF 2003
BETWEEN:
P. D. PHIRI t/a MALAYA
BUILDING
AND CIVIL ENGINEERING
CONTRACTORS…………PLAINTIFF
VERSUS
THE ATTORNEY GENERAL
……………………………DEFENDANT
CORAM: KALEMBERA, DEPUTY REGISTRAR
Chalamanda, Counsel for the Plaintiff
This is an order for
assessment of damages pursuant to a default judgment entered herein on the 1st
day of March 2004 in which it was adjudged that damages be assessed by the
Registrar.
The defendants despite being
served with the Notice for Assessment of damages did not attend. The assessment therefore proceeded in the
absence of the defendant. The plaintiff
called one witness Paston Domino Phiri, the plaintiff himself.
It was his testimony that he
is the Managing Director of the plaintiff company and that he entered into a
contract with the defendant for the construction of Chitipa District Hospital
and six health centres (Ex PDP 1). He
further informed the court that on certificate No. 8 he is claiming the sum of
K13,168,370.70 for the work actually done.
Further he claims the sum of K14,903,874.72 being loss of profit on the
balance of the contract sum. It was
further his claim that there be release of the bonds which are discharged
either upon completion of the work guaranteed or upon wrongful repudiation of
the contract on the employers’ part as is the case in this matter. As to the loss of use he informed the court
that the total loss comes to K4, 400.000.00.
He also needs the sum of K200, 000.00 for demobilisation of the plant,
vehicles and equipment and furniture and the total sum of K2, 657,812.00 for
the extension of time under claim number 3 of the summary of claims. The total sum comes to K35, 230,057.42 and
per the terms of the contract 65% was supposed to be paid in Euro currency, and
35% in Malawi currency which coverts to 392,316.89 Euros (K50, 478,277.52) and
K12, 330,520.00. The total therefore
comes to K62, 808,797.61 and from this sum a total sum of K7, 144,226.35 should
be paid directly by the defendant to the creditors whose list appears in the
schedule.
As already stated herein
there is a default judgment therefore the question of liability was already
settled. The defendant having failed to
attend the assessment the plaintiff’s testimony is unchallenged. What I need to do therefore is only to
determine the damages payable.
Mr Chalamanda, counsel for
the plaintiff has argued that according to law regarding damages where there
has been a breach of contract is such that a sum stated in a contract to be
payable in the event of breach of contract by one party to the other will be
liquidated damages if it represents a real attempt to agree in advance what the
damages would be in the event of breach of the contract (Ref African Lakes
Corporation Ltd –v- ORR [1923-60] ALR (MW) 25) This case further holds
that where damages caused by the breach cannot be ascertained, a sum stated in
the contract to be paid in the event of breach is prima facie to be regarded as
liquidated damages.
In the matter at hand per
the writ of summons and statement of claim the plaintiff claims for the
contract sum or the balance thereof; damages for repudiation of the said
agreement and costs. It has been held
that where contract work has been partly carried out and the contract is
brought to an end by the employers’ repudiation, the contractor is entitled to
be paid the value of the work done at contract prices and to claim in addition
damages the measure of which is normally the loss of profit on the unfinished
balance (Felton –v- Wharrie [1906] H.B.C. (4th ed.) p.
398(CA))
In the matter at hand the
plaintiff under Certificate Number 8 is claiming for the sum of K13, 168,370.70
being sums to be paid for the work actually done. There being no evidence to the contrary I do award the plaintiff
the sum of K13, 168,370.70 for work actually done. Furthermore under claim No. 5 on the summary of claims the sum of
K14, 903,974.72 being loss of profit on the balance of the contract sum. This being the consequence of the
defendants’ wrongful act I do award the plaintiff damages in the said sum of
k14, 903,874.72 being loss of profit on the balance of the contract sum. As to the loss of the use of equipment such
damages would calculated on the value of the plant and other articles of which
he had been wrongfully deprived (Ref. Keating on Building Contracts, by
Hon. Anthorny May, 1991 at p. 207).
In the present case the plaintiffs equipment is still retained by the
defendants whose calculated loss for use of the equipment comes to K4,
400.000.00. I do award this sum to
plaintiff as damages for loss of use of the equipment. I further award the plaintiff the sum of
K100, 000.00 as the cost of demobilisation of the equipment. The plaintiff is further awarded the sum of K2,
657,812.00 being for the extension of time for 45 weeks at K59, 062.50 per week
being acceptable practice in building contracts.
The total award on the
claims therefore comes to K35, 230,057.42.
The plaintiff further
indicated in his testimony that per the terms of the contract 65% was supposed
to be paid to the plaintiff in Euro Currency and 35% in Malawi Currency. As of 10th October 2003 at the
conversion rate of K128.6671 to 1 Euro 65% and 35% of the total claim of K35,
230,057.42 comes to a gross total claim of K62, 808,797.61. This having been a term of the contract I
therefore award the plaintiff damages as assessed the total sum of K62,
808,797.61 plus costs. I further order
that the sum of K7,144,226.35 be paid directly by the defendant from the total
award to the plaintiffs creditors whose list appears in the schedule (to be
supplied to the defendants).
Furthermore the defendants having wrongful repudiated the contract I
order for the release of the bonds.
MADE IN CHAMBERS this 1st
day of June 2004 at Blantyre.